Todays weekly project meeting took place today at 2pm between Chris Hewitt (PCC Project Manager) David Glew (Architect) and Paul Mendham (Principal Contractor).
I am pleased to report the project is now slightly ahead of schedule and the Chancel roof will be finished early next week. The scaffolding will then be reduced in size and moved to the nave. Hirst Consevation were also on site today and have been completing the final touchup of the chancel ceiling and rafters. Over the next three weeks chancel lighting will be installed and some stencil restoration will take place to the chancel east wall.
If anyone wants any roof tiles all those currently on the North Nave aspect are for sale. There are approx 8000 tiles ( 4500 plain 10.5" x 6.5" red dreadnought machine made & 3500 red club tiles made by Nostell). They are currently on the roof but are available from early December. If you want to see a sample close up, contact Chris Hewitt 01526 320645.
I am pleased to report the project is now slightly ahead of schedule and the Chancel roof will be finished early next week. The scaffolding will then be reduced in size and moved to the nave. Hirst Consevation were also on site today and have been completing the final touchup of the chancel ceiling and rafters. Over the next three weeks chancel lighting will be installed and some stencil restoration will take place to the chancel east wall.
If anyone wants any roof tiles all those currently on the North Nave aspect are for sale. There are approx 8000 tiles ( 4500 plain 10.5" x 6.5" red dreadnought machine made & 3500 red club tiles made by Nostell). They are currently on the roof but are available from early December. If you want to see a sample close up, contact Chris Hewitt 01526 320645.